How much is the salary of an SAP C_ACTIVATE13 certified professional?

In the end, the salary is decided by the company. The salary is dependent on the role of the candidate. However, the actual SAP C_ACTIVATE13 Certification Exam helps in certifying the candidate as a certified project manager. This certification is recognized by the companies in the market. Therefore, the candidate will be offered a higher salary. The salary of the C_ACTIVATE13 certified professional depends on the company, experience, job title, location of the company, etc. The average salary of the SAP C_ACTIVATE13 certified professional, who pass the exam with the assistance of the C_ACTIVATE13 Dumps is as follows:

  • In the United Kingdom: 77,000 GBP
  • In India: 55,000 INR
  • In Germany: 75,000 EUR
  • In the United States: 85,000 USD
  • In France: 66,000 EUR

 

NEW QUESTION 46
What solution operation framework can customers use to create a joint business and IT organisation that will secure transparency and efficiency of SAP implementation.

  • A. Customer centre of expertise
  • B. SAP Activate
  • C. Business transformation management methodology
  • D. SAP operations control centre

Answer: D

 

NEW QUESTION 47
What is the order of artifacts within the Technical Architecture and Infrastructure workstream in the Prepare phase?
Please choose the correct answer.
Response:

  • A. Hardware specification from Hardware Vendor -> Technical Strategy -> Parameters Hardware Sizing calculation -> Hardware Sizing results
  • B. Technical strategy -> Hardware specification from Hardware Vendor -> Parameters Hardware Sizing calculation -> Hardware Sizing results
  • C. Technical Strategy -> Parameters Hardware Sizing calculation -> Hardware Sizing results -> Hardware Specification from Hardware Vendor
  • D. Hardware specification from Hardware Vendor -> Parameters Hardware Sizing calculation -> Hardware Sizing results -> Technical Strategy

Answer: C

 

NEW QUESTION 48
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 correct answers to this question

  • A. SAP App centre
  • B. Blu -ray disks
  • C. SAP Solution Builder tool
  • D. SAP cloud appliance library

Answer: B,D

 

NEW QUESTION 49
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Please choose the correct answer.
Response:

  • A. During the daily SCRUM meeting
  • B. During the sprint review
  • C. During user acceptance testing
  • D. During the sprint retrospective

Answer: B

 

NEW QUESTION 50
In which phase do you create an ordered list of everything that is known to be needed in the product"?
Please choose the correct answer.
Response:

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: D

 

NEW QUESTION 51
Which of the following are benefits of using ready-to-use content?
There are 2 correct answers to this question

  • A. Minimized total cost of ownership
  • B. Fast time-to-value
  • C. Run SAP like a factory
  • D. CD Predictable results

Answer: B,D

 

NEW QUESTION 52
Where can you find Data Migration templates?

  • A. SAP roadmap viewer
  • B. SAP S/4HANA Migration cockpit
  • C. SAP cloud appliance library
  • D. SAP best practices explorer

Answer: B

 

NEW QUESTION 53
Which of the following is not a characteristic that the quality principles are based on?
Please choose the correct answer.
Response:

  • A. Experience of Typical Pitfalls
  • B. SAP Quality Award example winners
  • C. Best Practices
  • D. International standard

Answer: D

 

NEW QUESTION 54
Which estimation technique can be used in agile delivery approach to size the user Stories during sprint planning?

  • A. Detailed bottom-up effort estimate by the scrum master in story points based on the User story complexity
  • B. Product owners relative estimate of the effort that will be needed to implement the user story
  • C. Detailed bottom-up effort estimate that breaks each user story up into hours or shorter tasks
  • D. Relative estimate in ideal person days that reflects the best estimate provided By the project team

Answer: D

 

NEW QUESTION 55
What does the side-by-side extensibility option mean?

  • A. Context-aware SAP S/4HANA extensions, focused on tight integration
  • B. Extensibility based on the SAP cloud platform and published APIs
  • C. Transfer reporting to BW/4HANA
  • D. Have two SAP S/4HANA instances-one for standard code, and another for customer developments

Answer: B

 

NEW QUESTION 56
What is the final activity in the Realize phase of a new implementation of SAP S/4HANA cloud edition?
Please choose the correct answer.
Response:

  • A. Readiness check
  • B. Solution validation
  • C. Data migration
  • D. End-to-End walkthrough

Answer: D

 

NEW QUESTION 57
What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
Response:

  • A. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
  • B. Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
  • C. Plan -> Build -> Run -> Sustain
  • D. Plan -> Design -> Build -> Operate

Answer: A

 

NEW QUESTION 58
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition?
Please choose the correct answer.
Response:

  • A. Rapid prototyping
  • B. Full project SCRUM
  • C. SAP Best Practices
  • D. Project team training

Answer: C

 

NEW QUESTION 59
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:

  • A. Realize
  • B. Explore
  • C. Deploy
  • D. Prepare

Answer: C

 

NEW QUESTION 60
What term is used for a Ready-to-run SAP S/4HANA system with pre-built Solution Documentation, which supports End-to-End Processes for a specific industry so that the Project Team can focus on differentiation and innovation?
Please choose the correct answer.
Response:

  • A. Fully Activated Appliance
  • B. SAP Model Company
  • C. SAP Cloud Appliance Library
  • D. Best Practice System

Answer: B

 

NEW QUESTION 61
Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project.

  • A. Solution manager test suite
  • B. Requirement management
  • C. Focused build
  • D. Change request management

Answer: C

 

NEW QUESTION 62
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements?
There are 2 correct answers to this question.
Response:

  • A. Run SAP Like a Factory
  • B. Build SAP Like a Factory
  • C. Intelligent Enterprise
  • D. Always Connected

Answer: A,B

 

NEW QUESTION 63
In which phase will the customer develop a preliminary strategy for building A target operation and support organisational model?

  • A. Discover phase
  • B. Prepare phase
  • C. Run phase
  • D. Explore phase

Answer: B

 

NEW QUESTION 64
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:

  • A. Submit e-mail address via on-line form
  • B. Send e-mail to SAP contact address
  • C. Register on SAP Service Marketplace
  • D. Join SAP S/4HANA group on SAP Community Network

Answer: A

 

NEW QUESTION 65
What is SCRUM of SCRUMS?
Please choose the correct answer.
Response:

  • A. Mechanism for gathering and validating requirements
  • B. Integration meeting between the various project teams
  • C. Alternative to regular SCRUM process for smaller teams
  • D. Frequent inspection of code and configuration prior to quality gates

Answer: B

 

NEW QUESTION 66
Which of the following tools are used for rapid database migration?
There are 2 correct answers to this question.
Response:

  • A. SAP Solution Manager
  • B. Software Update Manager (SUM)
  • C. SWPM (software provisioning manager)
  • D. Database Migration Option (DMO)

Answer: B,D

 

NEW QUESTION 67
What does the content element of SAP activate provide? There are 3 correct answers to this question.

  • A. Business processes content
  • B. Integration content
  • C. Functional specifications for WRICEF development
  • D. End-user guides
  • E. Migration content

Answer: A,B,E

 

NEW QUESTION 68
......


How much does the SAP C_ACTIVATE13 Certification Exam cost?

The candidate must pay a non-refundable exam fee of 592 USD, for the SAP C_ACTIVATE13 Certification Exam.

 